How to prepare the final payment certificate, with a worked example

An interim certificate pays for the work so far. The final certificate closes the contract: it replaces every estimated quantity with the final measured one, finishes the advance, and leaves one figure open, the retention. The numbers below are an example contract, so you can check each line yourself.

Since 2013Vienna · Cairo · MuscatArabic and EnglishHosted and backed up by us

01What is the method in one line?

Final certificate = (final gross on final measured quantities − retention − the whole advance) − the net of all earlier certificates. The retention is then released on its own, on the date the contract sets, less any defect the contractor did not repair.

It is the same cumulative method as an interim certificate. What changes is that the quantities are final, so the differences from the contract quantities show up here.

02How is the final certificate different from an interim one?

Interim certificateFinal certificate
QuantitiesApproved to date, still openFinal measurement of every item, closed
Compared withThe previous certificateThe previous certificate and the contract value
AdvanceA share recoveredWhatever is left is recovered in full
RetentionHeldHeld, then released as the contract states
After itThe next certificateNo further certificate on this contract

03The example contract

The same contract as in the interim example: 1,000,000 in three bill of quantities items, 5% retention, and a 10% advance payment (100,000) recovered at 10% of each certificate's gross. Seven interim certificates have been issued. Tax is left out because it depends on the contract and the country.

04Step 1: the final measured quantity of every item

ItemContract quantityFinal quantityRateFinal valueDifference from contract
A. Reinforced concrete500 m³510 m³1,200612,000+ 12,000
B. Blockwork2,000 m²1,950 m²150292,500− 7,500
C. Plaster4,000 m²4,000 m²25100,0000
Total1,004,500+ 4,500

The work came to 1,004,500 against a contract of 1,000,000. Each difference sits on its own item, so the extra 10 m³ of concrete is a line somebody approved and not a figure that appeared in the total.

05Step 2: the deductions, to date

LineCalculationTo dateCertificates 1 to 7Final certificate
GrossFinal quantity × rate1,004,500950,00054,500
Retention5% of gross50,22547,5002,725
Advance recovery10% of gross, stopped at the advance100,00095,0005,000
NetGross − retention − recovery854,275807,50046,775

The final certificate pays 46,775. The two ways of reaching it agree: 854,275 − 807,500, and 54,500 − 2,725 − 5,000.

Note the advance: 10% of 54,500 is 5,450, but only 5,000 of the advance was still outstanding, so 5,000 is what is recovered. Recovery stops at the amount that was paid in advance.

06Step 3: the closing check

LineAmount
Advance paid at the start100,000
Net of all certificates, 1 to final854,275
Retention still held50,225
Total1,004,500

The three add up to the final gross. If they do not, something was paid outside a certificate or deducted twice, and this is the last point at which it is cheap to find.

07Step 4: releasing the retention

When the retention is released comes from the contract: all of it at the end of the defects liability period, or part at handover and the rest at the end. The arithmetic is the same either way.

LineCalculationAmount
Retention held5% of 1,004,50050,225
Defect repaired by othersThe repairer's bill− 3,000
Released to the contractor47,225

In the example one defect was not repaired by the contractor and was fixed by someone else for 3,000, with the bill behind it. The contractor receives 47,225, and in total 100,000 + 854,275 + 47,225 = 1,001,500, which is the 1,004,500 of work less the 3,000 repair.

08Where do final certificates usually go wrong?

09How does Revora do this?

Revora construction, by mbsystems, follows the same lines:

Ask for a demonstration on your own bill of quantities: info@mbsyss.com, or Cairo +20 100 520 5900, Muscat +968 7277 7269, Vienna +43 681 8411 0547. The price is given as a quote for your company.

Want to see it running?

Book a live walkthrough on your own data, or ask for a quote for your company.

info@mbsyss.com+43 681 8411 0547+20 100 520 5900 · +20 15 0000 1348+968 7277 7269