mbsystems

How to calculate a payment certificate, with a worked example

A payment certificate is arithmetic on approved quantities. The method below is the one most contracts use: work out everything to date, then subtract what was certified before. The numbers are an example contract, so you can check each line yourself.

Since 2013Vienna · Cairo · MuscatArabic and EnglishHosted and backed up by us

01What is the method in one line?

Net payable this period = (cumulative gross to date − cumulative retention − cumulative advance recovery − tax as the contract states) − the same net from the previous certificate.

Working cumulatively, and not period by period, means a mistake in an earlier certificate is corrected in the next one instead of being carried forward.

02The example contract

A contract worth 1,000,000 with three bill of quantities items, 5% retention, and a 10% advance payment (100,000) recovered at 10% of each certificate's gross. Tax is left out of the example because it depends on the contract and the country.

ItemUnitContract quantityRateContract value
A. Reinforced concretem³5001,200600,000
B. Blockworkm²2,000150300,000
C. Plasterm²4,00025100,000
Total1,000,000

03Step 1: the approved quantity per item, to date

For certificate No. 3 the contractor claims 320 m³ of concrete to date; the technical office measures and approves 300 m³. The certificate uses the approved figure, never the claim.

ItemApproved to dateApproved beforeThis periodGross to date
A. Concrete300 m³200 m³100 m³360,000
B. Blockwork800 m²400 m²400 m²120,000
C. Plaster0000
Total480,000

04Step 2: the deductions, to date

LineCalculationTo datePrevious certificatesThis certificate
GrossApproved quantity × rate480,000300,000180,000
Retention5% of gross24,00015,0009,000
Advance recovery10% of gross48,00030,00018,000
NetGross − retention − recovery408,000255,000153,000

Certificate No. 3 pays 153,000. The two ways of reaching it agree: 408,000 − 255,000, and 180,000 − 9,000 − 18,000.

05Step 3: what is left

06Where do certificates usually go wrong?

07How does Revora do this?

Revora construction, by mbsystems, follows the same lines:

Ask for a demonstration on your own bill of quantities: info@mbsyss.com, or Cairo +20 100 520 5900, Muscat +968 7277 7269, Vienna +43 681 8411 0547. The price is given as a quote for your company.

Want to see it running?

Book a live walkthrough on your own data, or ask for a quote for your company.

info@mbsyss.com+43 681 8411 0547+20 100 520 5900 · +20 15 0000 1348+968 7277 7269